Kenya: Transmission line connecting Menengai to national grid is almost done

Friday, 04 March 2016 18:35

In Kenya, the transmission line which is to connect the Menengai geothermal station to the national power grid will be completed in the next two months, Kenya Power Transmission Company in charge of construction announced. The 12.6km line will convey 105MW of energy from the plant to the grid.

The project includes, among others, the construction of 132kV sub-station in Menengai and the extension of the Soilo sub-station. ¨Power generated will be relayed to these two units.

The firm said it has finished construction of the power line, and completed 80% of works related to both sub-stations. Works have been estimated at $7.9 million.

Gwladys Johnson

Ecofin Agency provides daily coverage of nine key African economic sectors: public management, finance, telecoms, agribusiness, mining, energy, transport, communication, and education.
It also designs and manages specialized media, both online and print, for African institutions and publishers.

SALES & ADVERTISING

Benjamin FLAUX
bf@agenceecofin.com 
Téls: +41 22 301 96 11 
Mob: +41 78 699 13 72
Média kit : Download

EDITORIAL
redaction@agenceecofin.com

More information
Team
Publisher

ECOFIN AGENCY

Mediamania Sarl
Rue du Léman, 6
1201 Geneva
Switzerland

 

Ecofin Agency is a sector-focused economic news agency, founded in December 2010. Its web platform was launched in June 2011. ©Mediamania.

 
 

Please publish modules in offcanvas position.