Kenya: African Union commission grants $1 mln for Turkana geothermal plant

Monday, 13 November 2017 15:26

The African Union commission has provided for the Turkana geothermal plant, 101.5 million Kenyan Shillings (more than $980,000).

The grant was received by Olsuswa Energy, the firm in charge of the plant’s construction, and will be used to carry out technical studies as well as upgrade the infrastructure which is located in the Turkana County.

The project’s development will take place in two stages which will lead to installation of 140MW of capacity. The first will last between five and eight years, allowing to add 70MW to the national grid.

Actually, drilling works were to end this year, but it is very unlikely that this deadline will be met. Moreover, license-related issues are still being fixed with the government.

Gwladys Johnson

Ecofin Agency provides daily coverage of nine key African economic sectors: public management, finance, telecoms, agribusiness, mining, energy, transport, communication, and education.
It also designs and manages specialized media, both online and print, for African institutions and publishers.

SALES & ADVERTISING

Benjamin FLAUX
bf@agenceecofin.com 
Téls: +41 22 301 96 11 
Mob: +41 78 699 13 72
Média kit : Download

EDITORIAL
redaction@agenceecofin.com

More information
Team
Publisher

ECOFIN AGENCY

Mediamania Sarl
Rue du Léman, 6
1201 Geneva
Switzerland

 

Ecofin Agency is a sector-focused economic news agency, founded in December 2010. Its web platform was launched in June 2011. ©Mediamania.

 
 

Please publish modules in offcanvas position.