• Kenya achieved 70% rural electrification at $160–$700 per connection, averaging $500 per household (Kenya REA, 2021).
• Nigeria’s $410 billion grid-extension plan costs $25,000 per km with 42% system losses (TCN, Q4 2023).
• Adopting Kenya’s decentralized model, Nigeria could achieve universal access for ~$12.5 billion, a 97% saving.
The African Development Bank has confirmed the estimation that the continent requires $100 billion annually in infrastructure spending to achieve universal energy access. Nigeria alone has embedded in its 2060 Energy Transition Plan an investment envelope of $410 billion. Such figures rest on an assumption of large-scale centralized grid extension. Kenya’s experience provides a counter-example.
Through the Last Mile Connectivity Project and subsequent rural electrification programs, Kenya increased rural access rates from below 30 percent in 2010 to around 70 percent by 2020 at significantly lower unit costs. The comparison raises fundamental questions about the efficiency of Nigeria’s approach and suggests that decentralized, renewable-based systems offer an alternative pathway.
This analysis relies on verified cost data and regulatory documentation. For Nigeria, the Transmission Company of Nigeria (TCN) Q4 2023 performance report provides estimates of grid extension costs, transmission losses of 8.49 percent, and distribution losses of 33.62 percent. Kenya’s Rural Electrification Authority final project report (2021) offers detailed cost breakdowns of grid and micro-grid connection models.
Comparative data on rural electrification from the African Development Bank (2023, Mini-Grid Cost Benchmarking Study) and the World Bank’s Kenya Mini-Grid Experience: Lessons for Africa (2023) help contextualize the results. Household electrification gaps in Nigeria are estimated at 25 million unelectrified households, based on Energy Commission of Nigeria data and average household size of five. To test robustness, the analysis also includes a sensitivity case in which Nigerian mini-grid connection costs are doubled relative to Kenya’s.
Kenya’s Decentralized vs Nigeria’s Centralized Model
Kenya’s electrification push rested on small-scale renewable systems that could be deployed quickly and flexibly. The Last Mile Connectivity Project combined micro-grids of 5–100 kW capacity with low-voltage distribution networks serving clusters of 50–800 households. Costs ranged from $160 to $700 per household connection, averaging around $500, according to the Rural Electrification Authority (2021).
Total program costs amounted to about $5 billion. Public-private partnerships and the use of spatial analysis tools to optimize site selection accelerated rollout. By 2020, rural electrification had reached 70 percent of households. While challenges remain around tariff affordability and sustainability of operations, technical losses for these systems remain under 10 percent, significantly more efficient than national grid averages.
Nigeria has pursued an expansion strategy centered on grid extension. According to the TCN Q4 2023 report, transmission line construction costs average $25,000 per kilometer. Aggregate system losses are recorded at 42.11 percent, broken down into 8.49 percent transmission losses and 33.62 percent distribution losses, including commercial and collection inefficiencies.
Collection losses alone are estimated at 26.21 percent, while technical and commercial distribution losses stand at 21.55 percent. The Nigerian Electricity Regulatory Commission (NERC) identifies 20.06 percent as an efficient loss level, meaning current performance is more than double acceptable benchmarks. This systemic inefficiency inflates the capital envelope of the Energy Transition Plan to $410 billion, with full access not expected until 2060.
Implementation and Risks
The efficiency gap between Kenya and Nigeria is evident in connection costs. Extending Nigeria’s national grid requires an outlay of $25,000 per kilometer even before factoring in the per-household connection costs, while Kenya’s decentralized approach provided connections at $160–$700, or 35 to 156 times cheaper. Using Kenya’s average of $500 per household, connecting Nigeria’s 25 million unelectrified households would cost roughly $12.5 billion.
This contrasts sharply with the $410 billion projected by Nigeria’s centralized plan. A sensitivity analysis doubling the per-connection cost to $1,000 still yields a total cost of $25 billion, representing a 94 percent saving. These figures are consistent with benchmarks published by the African Development Bank (2023) and the World Bank (2023) on rural electrification project costs.
Adopting Kenya’s model in Nigeria would involve deploying modular solar mini-grids with prepaid smart metering and low-voltage alternating current distribution. Technical risks include battery degradation, requiring replacement every five to seven years, and the need to design for annual load growth of around 20 percent. Financial risks include exposure to currency fluctuations due to dollar-denominated equipment imports and potential shortfalls in maintenance funding.
Security and terrain also add localized risks in Nigeria’s northern and riverine regions. Risk mitigation strategies would involve standardized technical specifications, the establishment of sinking funds to cover maintenance, modular system design to allow for upgrades, and streamlined regulatory processes. Currently, licensing mini-grids in Nigeria takes 18–24 months, according to the Nigerian Electricity Regulatory Commission, suggesting the need for regulatory reform.
Idriss Linge
Lire aussi:
Except for Tunisia entering the Top 10 at Libya’s expense, and Morocco moving up to sixth ahead of A...
Circular migration is based on structured, value-added mobility between countries of origin and host...
BRVM listed the bonds of the FCTC Sonabhy 8.1% 2025–2031, marking Burkina Faso’s first securitiz...
CBE introduced CBE Connect in partnership with fintech StarPay. The platform enables cross-border...
President Tinubu approved incentives limited to the Bonga South West oil project. The project tar...
Nigeria lowered oil and gas signature bonuses to $3m–$7m from much higher past levels. The change applies to payments made before license awards...
DHL adds two Boeing 737-400 freighters to sub-Saharan Africa network Aircraft based in Lagos to cut transit times, boost trade reliability Expansion...
Standard Bank arranged a $250m facility to fund Aradel Energy’s expansion and acquisition plans. The deal allows Aradel to raise its stake in ND...
Mozambique expects Rovuma LNG construction to start within 12-18 months Improved security enables restart of major northern gas...
The Khomani Cultural Landscape is a cultural site located in northern South Africa, in the Northern Cape province, near the Kgalagadi Transfrontier Park....
Three African productions secured places among the 22 films competing for the Golden Bear at the 76th Berlin International Film Festival. Berlinale...