Electricity

Egypt: 19 out of 56 companies pulled out from renewable energy program

Friday, 25 November 2016 04:03

(Ecofin Agency) - With Nubian and Wadi pulling out from Egypt’s project to build renewable energy plants, a total of 19 developers have abandoned the initiative. The two firms were awarded contracts to build a 50 MW and 20 MW solar power plants, respectively, Daily News Egypt reports.

Egypt’s renewable energy purchase progam was launched in 2014 and its goal was the development of 4,300 MW of solar and wind power stations. Estimated to cost around $7 billion, 56 companies were picked to take carry it out. The ministry of energy said the companies that pulled out will not be fined or sanctioned in any way.

Explaining their decision to take the back door, the concerned firms mentioned a lack of determination from the regulatory organ to solve all issues that might have emerged at the development stage, the devaluation of the Egyptian pound and cumbersome procedures.

Gwladys Johnson

 
Finance


 
Mining


 
Telecom


 
Public Management


ECOFIN AGENCY offers a selection of articles translated from AGENCE ECOFIN. Founded in 2011, Agence Ecofin is a leader in Francophone Pan-African economic news, particularly in West and Central Africa. The agency publishes daily news on nine African economic sectors: Public Management, Finance, ICT, Agribusiness, Energy, Mining, Transport & Logistics, Communication, and Training.

AGENCE ECOFIN
Mediamania Sarl
Rue du Léman, 6
1201 Genève
Tél: +41 22 301 96 11

EDITORIAL TEAM
redaction@agenceecofin.com

ADVERTISING SALES
Benjamin FLAUX
bf@agenceecofin.com
Tél: +41 22 301 96 11
Mob: +41 78 699 13 72

 

Please publish modules in offcanvas position.