Mauritania EllaLink landing station 46% complete, officials say
Commissioning targeted for first quarter 2027
Cable to add 200 Gbps, reduce ACE reliance
Work on the landing station for the EllaLink international subsea cable in Mauritania is 46% complete, authorities said, adding that construction will be accelerated to meet the timeline for commissioning in the first quarter of 2027.
Ahmed Salem Ould Bede, Minister of Digital Transformation and Modernization of Administration, gave the update on Friday, Feb. 27, after meeting a high-level EllaLink delegation led by CEO Philippe Dumont. The discussions focused on technical progress and the steps needed to stay on schedule.
Progress on key components
Authorities said major components of the project are advancing as planned. Marine works, including the laying of the cable off the Mauritanian coast, are on schedule. The beach manhole, which serves as the junction between the subsea cable and the terrestrial network, is nearing completion.
Construction of the landing station and the terrestrial link connecting it to the beach manhole is also progressing steadily. Work on the station began in Nouadhibou in July 2025. Initial commissioning is now targeted for early 2027, rather than the previously scheduled 2028 date.
Strengthening international connectivity
The new cable will initially provide 200 gigabits per second (Gbps) of international capacity. The system can be upgraded to 500 Gbps, with a total design capacity of 12 terabits. Authorities said the project will strengthen Mauritania’s digital infrastructure by complementing the Africa Coast to Europe (ACE) cable.
Mauritania connected to the ACE cable in 2011 and continues to rely heavily on it for international connectivity. That reliance leaves the country exposed to disruptions. Repeated outages on the cable have caused nationwide internet and mobile service interruptions affecting public institutions, businesses and households. Even scheduled maintenance has led to temporary service cuts or sharp declines in connection speeds due to the absence of a fully operational backup link.
Isaac K. Kassouwi
Mediterrania Capital bought Australian Amcor's Moroccan packaging unit Enko Capital took ov...
Enko Capital acquires Servair’s fast-food unit in Côte d’Ivoire, including the Burger King franchi...
Standard Chartered arranges $2.33 billion for Tanzania railway project Funding support...
Central bank to release $1 billion in cash to curb black market demand Move aims to ease inf...
From eastern Chad, where measles and meningitis are spreading through overcrowded refugee camps, to ...
First Quantum to sell surplus sulfuric acid amid tightening supply Zambia disruptions, Middle East shortages cut sulfur supply...
Cabinda and Soyo terminals granted to SOGESTER for 20 years Move aims to cut transport costs and increase cargo and passenger traffic Strategy targets...
Revenue climbs 29% in Q1 2026 despite lower production Gold output drops across key mines, except Lafigué Higher gold prices offset volume...
Q1 copper production reaches 199,600 tons, up 19% year-on-year DR Congo output jumps 68%, led by Kamoto and Mutanda Group maintains 2026 outlook...
UK museum to return 45 Botswana artifacts after 150 years Items collected in 1890s; restitution follows Botswana request Return tied to...
The history of Kerma stretches back several millennia. Located in what is now northern Sudan, the site was inhabited as early as prehistoric times....