Launched in 2009, Cameroon’s program to build 10,000 social housing units, alongside the development of 50,000 serviced plots, has delivered 1,130 units out of 1,675 planned under its pilot phase.
Additional housing completed under the three-year Emergency Plan for Growth Acceleration (Planut), the Chinese-backed program and small and medium enterprise housing initiatives bring the total number of completed units to 3,585.
The figures were disclosed on February 12, 2026, in Douala by the Minister of Housing and Urban Development, Célestine Ketcha Courtès, during a key handover ceremony for 57 new homeowners in Mbanga Bakoko. According to the minister, 670 units have already been delivered in Douala, with 40 more expected by March and 30 in April.
Gradual Progress, Lingering Gaps
Since the first handovers in 2013, nearly 3,000 families have been housed in Douala, Yaoundé, Bafoussam, Limbé, Bamenda and Sangmélima, the minister said. The Mbanga Bakoko ceremony was presented as part of a gradual rollout, though overall progress remains well below initial objectives.
When she took office in 2018, only 420 units had been completed, highlighting early implementation challenges. The minister attributed delays to dysfunctions, including the limited financial and logistical capacity of some local small and medium enterprises, which led to work stoppages.
To revive the program, the government contracted new companies described as having proven performance, using exceptional agreements through the Ministry of Public Procurement. Authorities say this contractual shift was intended to address weaknesses in project execution.
Despite these adjustments, results remain modest compared with demand. Official estimates place Cameroon’s social housing deficit at around 2.5 million units, a situation authorities have described as acute.
Land and Tax Pressures Add New Constraints
To reduce the deficit, the government says it has opened discussions with several private partners — Pnhg, Addoha, Lafak and Wagas — to finalize conditions for launching new construction phases. However, access to land remains a structural bottleneck.
According to the housing ministry, discussions with the Ministry of State Property, Surveys and Land Tenure have advanced on land titles, with priority given to issuing them in 2026. A new fiscal measure could further complicate project economics.
Since January 2026, the government has ended the value-added tax exemption on social housing, introducing a 10% VAT on social housing operations, including interest, sales and rentals. The measure is expected to increase project costs and could affect affordability and access to social housing.
Frédéric Nonos, with Business in Cameroon
Mediterrania Capital bought Australian Amcor's Moroccan packaging unit Enko Capital took ov...
Enko Capital acquires Servair’s fast-food unit in Côte d’Ivoire, including the Burger King franchi...
Standard Chartered arranges $2.33 billion for Tanzania railway project Funding support...
Central bank to release $1 billion in cash to curb black market demand Move aims to ease inf...
From eastern Chad, where measles and meningitis are spreading through overcrowded refugee camps, to ...
First Quantum to sell surplus sulfuric acid amid tightening supply Zambia disruptions, Middle East shortages cut sulfur supply...
Campus to train youth in coding, data, and artificial intelligence Backed by Axian Group, France, and the European Union Project supports Togo’s...
Cabinda and Soyo terminals granted to SOGESTER for 20 years Move aims to cut transport costs and increase cargo and passenger traffic Strategy targets...
Revenue climbs 29% in Q1 2026 despite lower production Gold output drops across key mines, except Lafigué Higher gold prices offset volume...
UK museum to return 45 Botswana artifacts after 150 years Items collected in 1890s; restitution follows Botswana request Return tied to...
The history of Kerma stretches back several millennia. Located in what is now northern Sudan, the site was inhabited as early as prehistoric times....