The Board of Directors of the African Development Bank has approved a loan of UA 30 million ($42.9) million to finance the second phase of a major power transmission and interconnection project in Madagascar.
The Power Transmission Network Reinforcement and Interconnection Project in Madagascar (PRIRTEM-II) includes the construction of a 135-km, 220 kV interconnection line between the capital Antananarivo and the central industrial city of Antsirabé.
The project will help to feed the power generated by the Sahofika Hydropower Plant into the national grid, supplying some 8 million people with affordable, clean energy.
The financing comprises a loan of UA 20 million ($28.6 million) from the African Development Fund (ADF), the concessional lending window of the Bank, and a loan of UA 10 million ($14.3 million) from Pillar 1 of the Transition Support Facility (TSF), the Bank’s financing mechanism for fragile and transition countries.
The second phase of the project also includes the electrification of 19 villages in the Soanindrariny, Ambohidranandriana, Ambatomena and Ambohimiarivo municipal councils of central Madagascar, a country which, despite having huge renewable energy potential, has an electricity access rate of only 15% nationally and 6% in rural areas.
The Bank's country manager in Madagascar, Mohamed Cherif, said the project demonstrates the Bank’s commitment to increasing access to clean and low-cost energy. This, in turn, is expected to lead to the emergence of new economic opportunities, the development of industrialization, increased business competitiveness and job creation on the Indian Ocean island. As the sector’s lead donor, the Bank is already actively engaged in several transformative energy projects in Madagascar, including PRIRTEM-I and the Sahofika plant, both intricately linked to PRIRTEM-II.
The project is aligned with the Bank’s Country Strategy Paper (CSP) 2017-2021 for Madagascar, which focuses on the development of energy and transport infrastructure to support the country’s inclusive growth, as well as with the National Energy Policy (NPE).
The project is also in line with the Bank’s New Deal on Energy for Africa 2016-2025, as well as its High-5 priorities "Light up and Power Africa" and "Improve the quality of life for the people of Africa." The financing was approved on 11 December.

Togolese banks provided 16.2% of WAEMU cross-border credit by September 2025 Regional cross...
Microfinance deposits in Togo increased by CFA11.9 billion, a 2.7% rise in the second quarter of 2...
The BoxCommerce–Mastercard Partnership introduces prepaid cards, giving SMEs instant access to e...
Nigeria licensed Amazon’s Project Kuiper to operate satellite services from 2026, setting up dir...
Gas-fired plants and renewables anchor Mauritania’s electricity expansion plan New thermal, solar...
Kenya plans to cut value-added tax on agricultural inputs to 8% under the 2026 finance bill to lower production costs. The government plans to...
Izili acquired off-grid solar firm Qotto, active in Benin and Burkina Faso. The group secured $5 million in convertible bonds to support...
Nigeria approved the immediate launch of the Ogun State deep-sea port project. Authorities designed the port to ease congestion at Lagos...
DR Congo extended temporary import restrictions on selected goods for another 12 months. Authorities aim to cut the import bill and support...
Three African productions secured places among the 22 films competing for the Golden Bear at the 76th Berlin International Film Festival. Berlinale...
Ambohimanga is a hill located about twenty kilometres northeast of Antananarivo, in Madagascar’s Central Highlands. It holds a central place in the...