The Board of Directors of the African Development Bank has approved a loan of UA 30 million ($42.9) million to finance the second phase of a major power transmission and interconnection project in Madagascar.
The Power Transmission Network Reinforcement and Interconnection Project in Madagascar (PRIRTEM-II) includes the construction of a 135-km, 220 kV interconnection line between the capital Antananarivo and the central industrial city of Antsirabé.
The project will help to feed the power generated by the Sahofika Hydropower Plant into the national grid, supplying some 8 million people with affordable, clean energy.
The financing comprises a loan of UA 20 million ($28.6 million) from the African Development Fund (ADF), the concessional lending window of the Bank, and a loan of UA 10 million ($14.3 million) from Pillar 1 of the Transition Support Facility (TSF), the Bank’s financing mechanism for fragile and transition countries.
The second phase of the project also includes the electrification of 19 villages in the Soanindrariny, Ambohidranandriana, Ambatomena and Ambohimiarivo municipal councils of central Madagascar, a country which, despite having huge renewable energy potential, has an electricity access rate of only 15% nationally and 6% in rural areas.
The Bank's country manager in Madagascar, Mohamed Cherif, said the project demonstrates the Bank’s commitment to increasing access to clean and low-cost energy. This, in turn, is expected to lead to the emergence of new economic opportunities, the development of industrialization, increased business competitiveness and job creation on the Indian Ocean island. As the sector’s lead donor, the Bank is already actively engaged in several transformative energy projects in Madagascar, including PRIRTEM-I and the Sahofika plant, both intricately linked to PRIRTEM-II.
The project is aligned with the Bank’s Country Strategy Paper (CSP) 2017-2021 for Madagascar, which focuses on the development of energy and transport infrastructure to support the country’s inclusive growth, as well as with the National Energy Policy (NPE).
The project is also in line with the Bank’s New Deal on Energy for Africa 2016-2025, as well as its High-5 priorities "Light up and Power Africa" and "Improve the quality of life for the people of Africa." The financing was approved on 11 December.

Ethio Telecom has signed a new agreement with Ericsson to expand and modernize its telecom netwo...
The BCEAO cut its main policy rate by 25 basis points to 3.00%, effective March 16. Inflation...
EIB commits over €1 billion for renewable energy in sub-Saharan Africa Funding supports Miss...
Senegal launches 200 billion CFA bond in UEMOA Proceeds to fund 2026 budget, transformation agend...
MTN Zambia tests Starlink satellite service connecting phones directly from space Direct-to...
ACSA plans $695m upgrade and expansion of Cape Town airport Project includes new runway, terminals and expanded passenger facilities Expansion...
Zambia Railways secures $20m to rehabilitate six locomotives Upgraded locomotives expected back in service between May and December 2026 Project...
Deal reflects growing security cooperation amid Sahel terrorism threats Ghana plays key role in Accra Initiative regional security efforts The...
State company DRC Gold Trading aims to collect 15 tonnes of artisanal gold in 2026, far above volumes declared in recent years. The company plans to...
Located about forty kilometers east of Lomé along the Gulf of Guinea, Aného is one of the most historically significant towns in Togo. Nestled between a...
African-born artists generated $77.2 million in auction sales in 2024, down 31.9% year-on-year. Women artists accounted for about $22...