The Board of Directors of the African Development Bank has approved a loan of UA 30 million ($42.9) million to finance the second phase of a major power transmission and interconnection project in Madagascar.
The Power Transmission Network Reinforcement and Interconnection Project in Madagascar (PRIRTEM-II) includes the construction of a 135-km, 220 kV interconnection line between the capital Antananarivo and the central industrial city of Antsirabé.
The project will help to feed the power generated by the Sahofika Hydropower Plant into the national grid, supplying some 8 million people with affordable, clean energy.
The financing comprises a loan of UA 20 million ($28.6 million) from the African Development Fund (ADF), the concessional lending window of the Bank, and a loan of UA 10 million ($14.3 million) from Pillar 1 of the Transition Support Facility (TSF), the Bank’s financing mechanism for fragile and transition countries.
The second phase of the project also includes the electrification of 19 villages in the Soanindrariny, Ambohidranandriana, Ambatomena and Ambohimiarivo municipal councils of central Madagascar, a country which, despite having huge renewable energy potential, has an electricity access rate of only 15% nationally and 6% in rural areas.
The Bank's country manager in Madagascar, Mohamed Cherif, said the project demonstrates the Bank’s commitment to increasing access to clean and low-cost energy. This, in turn, is expected to lead to the emergence of new economic opportunities, the development of industrialization, increased business competitiveness and job creation on the Indian Ocean island. As the sector’s lead donor, the Bank is already actively engaged in several transformative energy projects in Madagascar, including PRIRTEM-I and the Sahofika plant, both intricately linked to PRIRTEM-II.
The project is aligned with the Bank’s Country Strategy Paper (CSP) 2017-2021 for Madagascar, which focuses on the development of energy and transport infrastructure to support the country’s inclusive growth, as well as with the National Energy Policy (NPE).
The project is also in line with the Bank’s New Deal on Energy for Africa 2016-2025, as well as its High-5 priorities "Light up and Power Africa" and "Improve the quality of life for the people of Africa." The financing was approved on 11 December.

Except for Tunisia entering the Top 10 at Libya’s expense, and Morocco moving up to sixth ahead of A...
African startup M&A hits record 67 deals in 2025 Consolidation driven by funding pressures and ex...
Urban employment reached 53.7% in WAEMU in early 2025 Most jobs remain informal, low-paid, and in...
CBE introduced CBE Connect in partnership with fintech StarPay. The platform enables cross-border...
Moniepoint, Opay, Kuda, and others gain national status with tighter oversight A naira 5 billion ...
The African Union and the United Kingdom agreed to hold a high-level strategic meeting in London in early 2026. AU Commission President Mahamoud...
Eramet ended the mandate of CEO Paulo Castellari and appointed Chair Christel Bories as interim chief executive. The board cited differences over...
Aura Energy plans to raise A$20 million ($13 million) to fund development of the Tiris uranium project in Mauritania. The company targets a final...
Khartoum International Airport handled its first commercial passenger flight after nearly three years of closure caused by the war. Sudan Airways...
Manovo-Gounda-St Floris National Park is one of the largest protected areas in Central Africa. Located in the northeastern part of the Central African...
Streaming dominates music, reshaping royalties and artist income worldwide Sub-Saharan Africa grows fast, but payouts stay far lower Platform, region,...